Aliança Energia

Aliança Geração de Energia S.A. is a Brazilian company operating in the electricity generation and commercialization market, headquartered in Belo Horizonte, Minas Gerais.

Founded in 2015, the company is already among the largest private electricity generation companies in Brazil, contributing to the country’s private generation park.

Aliança Energia is also betting on future investments in energy generation from various sources, such as wind, solar, among others, to ensure the diversification and sustainability of its operations.

Purpose

Energies that drive lives.

Mission

Generate and trade energy creating value, prosperity and quality of life.

Vision

To be excellent in managing renewable energy generation assets, with a focus on operational efficiency, valuing people and socio-environmental responsibility.

Values

Life comes first.
Social and environmental responsibility.
Continuous search for excellence.
Cooperation to move forward.
Integrity is non-negotiable.
Protagonism to make it happen.

Our History

Learn a little more about the history of our company.

2025
2025

Corporate Restructuring

On September 18, the process of entry of Global Infrastructure Partners (GIP) as a shareholder of the Aliança Energia was concluded, with a 70% stake in the share capital, alongside Vale, which maintains 30%.

New Assets

On September 1st, the inclusion of two new own assets was made official, namely the Sol do Cerrado Photovoltaic Plant and the Risoleta Neves Hydroelectric Power Plant.

2024
2024

Purpose and Values

Launch of the Aliança Energia Purpose and revised Values.

Corporate Restructuring

On August 13, the process of purchase of Cemig shares (45%) by Vale was concluded.

Acauã Wind Complex

On May 21, the official inauguration event of the Acauã Wind Complex was held in São Vicente (RN).

2023
2023

Vision

Aliança Energia Vision Update.

Gravier Wind Power Plant

On November 28, the official inauguration event of the Gravier Wind Power Plant was held in Icapuí (CE).

Acauã Wind Complex

Acauã Wind Complex (RN) starts gradual operation with the generation of the first megawatts

2022
2022

Gravier Wind Power Plant

Gravier Wind Power Plant (CE) starts full commercial operation of 71.4 MW.

2021
2021

Implementation of new projects

Beginning of the construction of the Gravier Wind Power Plant, Acauã Wind Complex and 230 kV SE Acauã - SE Lagoa Nova II Transmission Line.

2020
2020

Obtaining environmental permits

Obtaining the Installation Licenses for the Acauã Wind Complex (RN) and the Installation and Operation License (LIO) for the Wind Farm (CE).

2019
2019

Approval of new projects

Acauã Wind Complex (RN) and Gravier Wind Farm (CE).

2018
2018

Mission, Vision and Values

Definition of the Mission, Vision and Values of the Aliança Energia.

2017
2017

CESI

Start of commercial operations of the Santo Inácio Wind Complex.

2016
2016

New headquarters

Inauguration of the headquarters in Belo Horizonte (MG).

2015
2015

Conclusion of the constitution of Aliança Geração de Energia S.A.

On February 27, 2015, the transaction for the constitution of the joint venture was concluded, with the increase of capital stock in Aliança Energia and the contribution of the aforementioned assets. In February, the company's first employees were hired.

2014
2014

Formalization of the joint venture

On August 5, 2014, Aliança Energia was formally constituted, followed by the legal formalities, regulatory approvals and compliance with conditions precedent.

2013
2013

Agreement for the constitution of Aliança Geração de Energia S.A.

The shareholders, who were already partners in hydroelectric projects, formed Aliança Energia on December 19, 2013, when they entered into an agreement involving their respective interests in the power generation assets – Hydroelectric Power Plants: Porto Estrela, Igarapava, Funil, Capim Branco I and II, Aimorés and Candonga.

Corporate Structure

Aliança Geração de Energia S.A. represents the union of two big names in their respective sectors: Vale and Cemig. The companies, which have solid experience in the energy sector, ensure the purchase of a large part of the energy generated by the new company.

Shareholding Structure

Vale is a global company, headquartered in Brazil and present in more than 30 countries on five continents. Operating in the areas of mining, logistics, energy and steel, it is a leader in the production of iron ore and the second largest producer of nickel.

The Cemig Group is one of the most solid and important groups in the electric power segment in Brazil, with interests in more than 200 companies and consortia, with business in 23 Brazilian states and Chile.